Which of the follow...
 
Notifications
Clear all

Which of the following are critical for the project manager to provide?

1 Posts
1 Users
0 Likes
87 Views
(@soquirandolph)
Posts: 729
Noble Member
Topic starter
 

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.

Which of the following are critical for the project manager to provide?

  • A . Cost, schedule, organizational chart, and risks/issues
    B. Risks/issues, cost, RACI chart, and action items
    C. Schedule, cost, risks/issues, and milestones
    D. Action items, organizational chart, schedule, and NDA

Show Answer Hide Answer

Suggested Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326
 
Posted : 13/12/2022 7:19 am

Latest CompTIA PK0-004 Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: