While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:

1 Posts
1 Users
0 Likes
116 Views
(@soquirandolph)
Posts: 729
Noble Member
Topic starter
 

While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:

  • A . quality plan.
    B. project management plan.
    C. risk register.
    D. process diagram.

Show Answer Hide Answer

Suggested Answer: A
 