Which Scrum accountability must do all the work to make sure the Product Backlog items conform to the definition of "Done"?

1 Posts
1 Users
0 Likes
100 Views
(@ripaharris)
Posts: 737
Noble Member
Topic starter
 

Which Scrum accountability must do all the work to make sure the Product Backlog items conform to the definition of "Done"?

  • A . The Developers
    B. The Scrum Master
    C. The Product Owner

Show Answer Hide Answer

Suggested Answer: A

Explanation:

Developers are the people in the Scrum Team that are committed to creating any aspect of a usable Increment each Sprint.
 