During a Sprint, when is new work added to the Sprint Backlog?
- A . As soon as possible after identification.
B. When the Developers have talked to the Product Owner.
C. When the Scrum Master allows it.
Suggested Answer: A
Explanation:
The Developers do not need to talk to the Product Owner if they identify that additional work has to be done to achieve the Sprint Goal. But they have to do so if they want to re-negotiate the Sprint scope.
Explanation:
The Developers do not need to talk to the Product Owner if they identify that additional work has to be done to achieve the Sprint Goal. But they have to do so if they want to re-negotiate the Sprint scope.