Which of the following were MOST likely missed during project planning?

1 Posts
1 Users
0 Likes
101 Views
 Tuan
(@shippertuan)
Posts: 713
Noble Member
Topic starter
 

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it.

Which of the following were MOST likely missed during project planning?

  • A . Issue log and process diagram
    B. Resource analysis and Gantt chart
    C. Stakeholder analysis and communication plan
    D. Scatter chart and scope analysis

Show Answer Hide Answer

Suggested Answer: B
 