Which of the following tools should the project team select to determine the possible origins of the increased costs?

1 Posts
1 Users
0 Likes
87 Views
(@rickielewis)
Posts: 713
Noble Member
Topic starter
 

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns.

Which of the following tools should the project team select to determine the possible origins of the increased costs?

  • A . Pareto chart
    B. Fishbone diagram
    C. Process diagram
    D. Run chart

Show Answer Hide Answer

Suggested Answer: B
 