Which of the follow...
 
Notifications
Clear all

Which of the following strategies is the project manager trying to apply?

1 Posts
1 Users
0 Likes
73 Views
(@palomamikel)
Posts: 733
Noble Member
Topic starter
 

A project needs two more months of work to be completed, but the deadline is in 35 days. The project

manager heard the company recently hired an experienced person. The project manager scheduled a meeting with the functional manager to negotiate bringing the experienced person to the team.

Which of the following strategies is the project manager trying to apply?

  • A . Exploit
    B. Mitigate
    C. Accept
    D. Transfer

Show Answer Hide Answer

Suggested Answer: A
 
Posted : 28/01/2023 6:58 pm

Latest CompTIA PK0-004 Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: