Notifications
Clear all
Topic starter
A project manager noticed the development team supporting a project does not have
sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions.
Which of the following strategies is the project manager applying?
- A . Accepting
B. Mitigating
C. Avoiding
D. Transferring
Suggested Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238
Posted : 08/12/2022 5:44 pm