A software upgrade project has been postponed because it may impact a critical business system.

Which of the following strategies has been applied?

  • A . Accept risk
    B. Mitigate risk
    C. Avoid risk
    D. Exploit risk

Show Answer Hide Answer

Suggested Answer: C
 