Which of the follow...
 
Notifications
Clear all

Which of the following should the project manager do to obtain the resources?

1 Posts
1 Users
0 Likes
118 Views
(@bulluckrolando)
Posts: 664
Noble Member
Topic starter
 

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.

Which of the following should the project manager do to obtain the resources?

  • A . The project manager should identify and document the reasons for the additional resources in a change request.
    B. The project manager should hire additional resources temporarily to complete the project.
    C. The project manager should terminate the project until additional resources are added to the project.
    D. The project manager should ask the project team members to take on more tasks to complete the project on time.

Show Answer Hide Answer

Suggested Answer: A
 
Posted : 12/02/2023 8:37 am

Latest CompTIA PK0-004 Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: