Which of the following should the project manager do FIRST to ensure all parties have the same level of information?

1 Posts
1 Users
0 Likes
91 Views
 Man
(@shortinoman)
Posts: 733
Noble Member
Topic starter
 

A recently added stakeholder is unaware of critical changes that will affect the department.

Which of the following should the project manager do FIRST to ensure all parties have the same level of information?

  • A . The project manager should check the project management plan to determine how the
    project should be managed and controlled.
    B. The project manager should check the communications plan to ensure stakeholders are
    included on any key messages.
    C. The project manager should check the meeting agenda to ensure the stakeholder is invited to all meetings.
    D. The project manager should ensure meeting minutes are distributed to all project members.

Show Answer Hide Answer

Suggested Answer: B
 