Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

1 Posts
1 Users
0 Likes
80 Views
(@cainsmarshall)
Posts: 692
Noble Member
Topic starter
 

An organization has multiple projects that are taking place simultaneously.

Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

  • A . PMO
    B. Project sponsor
    C. Project coordinator
    D. HR

Show Answer Hide Answer

Suggested Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82
 