Which of the following project documents should be used to record the occurrence of an unplanned event?

1 Posts
1 Users
0 Likes
110 Views
(@sextoncletus)
Posts: 695
Noble Member
Topic starter
 

Which of the following project documents should be used to record the occurrence of an unplanned event?

  • A . Action log
    B. Risk log
    C. Change log
    D. Issue log

Show Answer Hide Answer

Suggested Answer: D

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 327
 