Which of the following is MOST likely to be the first document created by the project manager?

1 Posts
1 Users
0 Likes
80 Views
(@rippebrain)
Posts: 721
Noble Member
Topic starter
 

A vendor has accepted a proposed project from a customer.

Which of the following is MOST likely to be the first document created by the project manager?

  • A . Project charter
    B. Project management plan
    C. Project statement of work
    D. Project schedule

Show Answer Hide Answer

Suggested Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299
 