A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?
- A . Project charter
B. Project management plan
C. Project statement of work
D. Project schedule
Suggested Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299