A stakeholder is unaware of a project’s status.

Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

  • A . Status report
    B. Organizational chart
    C. RACI matrix
    D. Meeting minutes
    E. Communication plan

Show Answer Hide Answer

Suggested Answer: A,D

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
 