Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

1 Posts
1 Users
0 Likes
124 Views
(@sextoncletus)
Posts: 695
Noble Member
Topic starter
 

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

  • A . Planned value
    B. Schedule variance
    C. Acceptable variance
    D. Cost variance
    E. Earned value

Show Answer Hide Answer

Suggested Answer: D,E
 