A PM notes a feature that was delivered does not appear in the latest requirement document. The PM
immediately submits a change request for remediation.
Which of the following actions has the PM omitted?
- A . Identifying the risk
B. Obtaining approval from the CCB
C. Evaluating the impact of the risk
D. Communicating to stakeholders
Suggested Answer: B