Using the attached ...
 
Notifications
Clear all

Using the attached schedule, which of the following is the critical path?

1 Posts
1 Users
0 Likes
89 Views
(@rickielewis)
Posts: 713
Noble Member
Topic starter
 

A project manager has developed the initial schedule for an upcoming project.

Using the attached schedule, which of the following is the critical path?

  • A . 12 days
    B. 14 days
    C. 16 days
    D. 17 days

Show Answer Hide Answer

Suggested Answer: A
 
Posted : 24/11/2022 3:19 pm

Latest CompTIA PK0-004 Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: