The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.
This type of analysis is an example of which of the following?
- A . Cost performance index
B. Risk mitigation
C. Schedule variance
D. Cost variance
Suggested Answer: C