The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.

This type of analysis is an example of which of the following?

  • A . Cost performance index
    B. Risk mitigation
    C. Schedule variance
    D. Cost variance

Show Answer Hide Answer

Suggested Answer: C
 