A resource is assigned to two projects with two scheduled tasks that complete at the same time.

This is known as:

  • A . shared resource contention
    B. intraproject resource contention
    C. interproject resource contention
    D. dedicated resource contention

Show Answer Hide Answer

Suggested Answer: C
 