The summary duration of each path is below:

1 Posts
1 Users
0 Likes
136 Views
(@swindellguillermo)
Posts: 719
Noble Member
Topic starter
 

There are four parallel paths on a network diagram.

The summary duration of each path is below:

A, C, G: 10 weeks

A, B, F: 8 weeks

D, E, H: 12 weeks

D, B, F: 7 weeks

Which of the following tasks are on the critical path?

  • A . A, C, G
    B. A, B, F
    C. D, E, H
    D. D, B, F

Show Answer Hide Answer

Suggested Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175
 