The project manager has collected the information below:

1 Posts
1 Users
0 Likes
102 Views
(@tsuchiuramanual)
Posts: 747
Noble Member
Topic starter
 

A project manager is creating the monthly report for top management.

The project manager has collected the information below:

AC = 100

PV = 80

EV = 120

Based on this information, the CPI reflects which of the following about the project?

  • A . It is under budget.
    B. It is over budget.
    C. It is ahead of schedule.
    D. It is behind schedule.

Show Answer Hide Answer

Suggested Answer: A

Explanation:

“The cost performance index (CPI)

is calculated this way:

CPI = EV / AC”

Excerpt From: Kim Heldman. “CompTIA Project+ Study Guide.” iBooks.
 