In which of the following categories does a business process change fit?
- A . Project change
B. Organizational change
C. General change
D. Departmental change
Suggested Answer: B
Explanation:
“Business process changes typically occur within the organization. An example of a business process change is automating a process that previously was performed on paper. If your project has anything to do with this process or is impacted by the process, changes will be coming your way”
Excerpt From: Kim Heldman. “CompTIA Project+ Study Guide.” iBooks.
Explanation:
“Business process changes typically occur within the organization. An example of a business process change is automating a process that previously was performed on paper. If your project has anything to do with this process or is impacted by the process, changes will be coming your way”
Excerpt From: Kim Heldman. “CompTIA Project+ Study Guide.” iBooks.