Based on this information, which of the following can the key stakeholders determine about the project?

1 Posts
1 Users
0 Likes
87 Views
(@ferronigiovanni)
Posts: 731
Noble Member
Topic starter
 

In a project with a of $235,000, the CPI is 0.80, and the SPI is 1.20.

Based on this information, which of the following can the key stakeholders determine about the project?

  • A . The project is under budget and ahead of schedule.
    B. The project is over budget and ahead of schedule.
    C. The project is under budget and behind schedule.
    D. The project is over budget and behind schedule.

Show Answer Hide Answer

Suggested Answer: B
 
Posted : 14/02/2023 12:57 am