Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
- A . SCRUM retrospective
B. Kickoff meeting
C. Budget baseline
D. Risk review
Suggested Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306