A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

1 Posts
1 Users
0 Likes
152 Views
(@pesterfieldrayford)
Posts: 681
Noble Member
Topic starter
 

A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

  • A . durations.
    B. tasks.
    C. critical path.
    D. resources.

Show Answer Hide Answer

Suggested Answer: B
 