When the NetEco management system is sold in the market, which of the following situations does not need to submit RM to the management system RAT for decision-making? ( )

1 Posts
1 Users
0 Likes
93 Views
(@ruleychuck)
Posts: 689
Noble Member
Topic starter
 

When the NetEco management system is sold in the market, which of the following situations does not need to submit RM to the management system RAT for decision-making? ( )

  • A . When there are three-party equipment access requirements in the project.
    B. When there is non-standard function customization in the project, the existing products cannot meet it.
    C. When supporting FusionModule products for sale
    D. When large-scale DC project network management is sold separately.

Show Answer Hide Answer

Suggested Answer: C
 
Posted : 10/02/2023 3:03 pm