Universal Containers is building a custom application on the Force.com platform. There is a budget and release date that has been set by the board of directors, but the application must meet the requirements that will be submitted and voted on by a public user community.
What is the risk associated with the scenario?
- A . The requirements should not be solicited by an external community
B. The project is not using the Waterfall methodology
C. The project is not using an Agile methodology
D. The requirements are unknown and the release date has been set.
Suggested Answer: D