An organization suffered an outage and a critical system took 90 minutes to come back online. Though there was no data loss during the outage, the expectation was that the critical system would be available again within 60 minutes.
Which of the following is the 60-minute expectation an example of:
- A . MTBF
- B . RPO
- C . MTTR
- D . RTO
Suggested Answer: D