Who should be consulted first when calculating the % Complete and Accurate?

1 Posts
1 Users
0 Likes
170 Views
(@katterjohnoctavio)
Posts: 721
Noble Member
Topic starter
 

Who should be consulted first when calculating the % Complete and Accurate?

  • A . Testers
    B. The lead developer
    C. End users
    D. The people responsible for the next step

Show Answer Hide Answer

Suggested Answer: D

Explanation:

Percent Complete and Accurate (%C&A) ~ Percent of work that the next station could process as-is. Ask people responsible for the next step about the % complete and accurate of the current step.
 