Which statement illustrates the biggest bottleneck?

  • A . LT = 6 days, PT = 5 days, %C&A = 100%
    B. LT = 5 days, PT = 2.5 DAYS, %C&A = 100%
    C. LT = 10 days, PT = 0.5 days, %C&A = 100%
    D. LT = 1 day, PT = 0.5 days, %C&A = 90%

Show Answer Hide Answer

Suggested Answer: C

Explanation:

Bottle neck. The operation or function with the lowest capacity, usually the operation with the longest cycle time per unit. The bottle neck sets the limit for the production pace and thus the capacity of the entire process. The process efficiency is uses to detect bottlenecks.Process Efficiency = Process time / Lead TimeIr our case, the lowest process efficiency time is 0,005 = 0,5 days / 10 days
 