When preparing a DevOps backlog, prioritizing features using WSJF includes which two factors? (Choose two.)
- A . Cost of delay
B. Business value
C. Total count of items on the Program Backlog
D. Team velocity
E. Duration/job size
Suggested Answer: A,E
Explanation:
" https://www.scaledagileframework.com/wsjf/
Explanation:
" https://www.scaledagileframework.com/wsjf/