Which two of the following answers are not correct about the Product Owner accountability (role = outdated term)?

1 Posts
1 Users
0 Likes
153 Views
(@delillovicente)
Posts: 721
Noble Member
Topic starter
 

Which two of the following answers are not correct about the Product Owner accountability (role = outdated term)?

  • A . The Product Owner decides which developer does what.
    B. The Product Owner has to participate in the Daily Scrum.
    C. The Product Owner measures the progress of a release.
    D. The Product Owner is responsible for maximizing the value.

Show Answer Hide Answer

Suggested Answer: A,B

Explanation:

The Scrum team is "self-organized" - that means that they decide on their own who does which task. Only the Development Team members have to participate in the Daily Scrum. Others like the Product Owner can attend (they shouldn't talk).
 