Which of the following describes best the Sprint Review?

1 Posts
1 Users
0 Likes
87 Views
(@castilogonzalo)
Posts: 663
Noble Member
Topic starter
 

Which of the following describes best the Sprint Review?

  • A . It is a meeting for the inspection of the Increment and to collect feedback.
    B. It is a meeting to do the controlling and evaluation in regards to the developers work.
    C. It is a formal meeting to receive the approval for the work that was done.

Show Answer Hide Answer

Suggested Answer: A

Explanation:

It is not about controlling - it is about reviewing the new Increment and receiving feedback. The meeting is a "formal opportunity" for inspection and adaption, but no "formal meeting".
 