Which of the following actions should a Scrum Master do to start a new Project?

1 Posts
1 Users
0 Likes
89 Views
(@soquirandolph)
Posts: 729
Noble Member
Topic starter
 

Which of the following actions should a Scrum Master do to start a new Project?

  • A . Assign the first tasks to the Developers.
    B. Ensure that the developers have access to the systems.
    C. Ask the team lead to explain the product roadmap.
    D. Ask the Product Owner to explain the project, general requirements, project history and context.

Show Answer Hide Answer

Suggested Answer: D

Explanation:

There are no team leads in scrum. The team is self-organizing, no one assigns tasks to the developers.
 