When should testing tasks be done?
- A . After the Sprint.
B. Before the release.
C. In the Testing Sprint.
D. During the Sprint.
Suggested Answer: D
Explanation:
Everything that has to be done to transform a Product Backlog item in a new Product Increment (including testing) has to be done during the Sprint.