When n Scrum teams are working on a product, there should always be only 1 Product Owner but 1-n Scrum Masters.
- A . False
B. True
Suggested Answer: B
Explanation:
When there are n teams in a project, there are:
- 1 Product Backlog
- n Sprint Backlogs each Sprint
- 1 Product Owner
- n Scrum Master roles
Explanation:
When there are n teams in a project, there are:
- 1 Product Backlog
- n Sprint Backlogs each Sprint
- 1 Product Owner
- n Scrum Master roles