When is a Sprint over according to Scrum?
- A . When the Scrum Master cancels the Sprint.
B. When the time box is over.
C. When all the work in the Sprint Backlog is "done".
D. When the Product Owner cancels the Sprint.
Suggested Answer: B,D
Explanation:
Only the Product Owner has the authority to cancel a Sprint.
Explanation:
Only the Product Owner has the authority to cancel a Sprint.