When does one Developer take ownership of a Sprint Backlog item?
- A . During the Daily Scrum.
B. During the Sprint Planning meeting.
C. They don't.
Suggested Answer: C
Explanation:
Sprint Backlog items are owned by the whole Development Team.
Explanation:
Sprint Backlog items are owned by the whole Development Team.