The Sprint Review is considered as a "formal meeting".

1 Posts
1 Users
0 Likes
81 Views
(@pesterfieldrayford)
Posts: 681
Noble Member
Topic starter
 

The Sprint Review is considered as a "formal meeting".

  • A . True
    B. False

Show Answer Hide Answer

Suggested Answer: B

Explanation:

Be careful with the word "formal". Scrum. org uses the word "formal" in two different ways:
 