The Developers have some trouble to understand a Sprint Backlog item - what should they do?
- A . Ask the Scrum Master to explain it to them.
B. Don't touch the item until the Sprint Review to discuss it with the Product Owner again.
C. Collaborate with the Product Owner immediately to receive a better understanding.
Suggested Answer: C
Explanation:
The Product Owner is responsible to explain the items. It is the responsibility of the Developers to start the discussion as soon as possible and not wait until the Sprint End.
Explanation:
The Product Owner is responsible to explain the items. It is the responsibility of the Developers to start the discussion as soon as possible and not wait until the Sprint End.