The Definition of Done increases the transparency and is used by the Developers to forecast how many items can be picked from the Product Backlog.
- A . False
B. True
Suggested Answer: B
Explanation:
In addition, the Definition of Done can be improved during the project. The Definition of Done should not be changed during the Sprint.
Explanation:
In addition, the Definition of Done can be improved during the project. The Definition of Done should not be changed during the Sprint.