Scrum Teams are allowed to use burn-up charts instead of burn-down charts.
- A . True
B. False
Suggested Answer: A
Explanation:
There are different things that can help them in this forecast, but they are all guesses and the Product Owner has to consider everything and adjust the forecast before presenting it to the stakeholders.
It\'s very common to use burn-down charts in Agile, but it\'s up to the Product Owner to decide how they want to measure and visualize performance of the project, and up to the developers to decide how they want to do it for Sprints.
Explanation:
There are different things that can help them in this forecast, but they are all guesses and the Product Owner has to consider everything and adjust the forecast before presenting it to the stakeholders.
It\'s very common to use burn-down charts in Agile, but it\'s up to the Product Owner to decide how they want to measure and visualize performance of the project, and up to the developers to decide how they want to do it for Sprints.