A baselined Product Backlog is called?
- A . Sprint Backlog.
B. The Product Backlog is not baselined.
C. Release Plan.
Suggested Answer: B
Explanation:
Scrum.org interprets baseline as keeping the subject fixed, and therefore, believes that there are no baselines in Scrum.
Explanation:
Scrum.org interprets baseline as keeping the subject fixed, and therefore, believes that there are no baselines in Scrum.