Config Advisor reports that you have a single point of failure on a stack of shelves.
After investigation, you have assigned the following ports to each stack:
stack 1 - ports 0a and 0b
stack 2 - ports 3a and 4b
stack 3 - ports 4a and 3b
In this scenario, which two changes would you make to the cabling to solve the problem? (Choose two.)
- A . Cable stack 3 to ports 4a and 0b.
B. Cable stack 2 to ports 4a and 4b.
C. Cable stack 1 to ports 0a and 3b.
D. Cable stack 3 to ports 3a and 3b.
Suggested Answer: BC