A company has decided to move its datacenter to an laaS provider. The company stakeholders are concerned about their ISP being a single point of failure .
Which of the following will the network administrator MOST likely recommend to mitigate this nsk?
- A . Adopt a multicloud strategy to ensure access in case of an outage.
- B . Contract a secondary ISP to provide another connection.
- C . Lease additional office space for use in the event of a disaster.
- D . Get an additional Internet connection from the current ISP
Suggested Answer: B