A company discovers that planned costs are being calculated incorrectly due to missing configurations.

You need to configure the system to prevent calculation of the planned cost for items that are missing the following:

• a valid bill of materials (BOM) version

• a valid cost price

In which two locations can you configure the validation?

  • A . Product information management parameters
    B. Inventory and warehouse management parameters
    C. Released products
    D. Calculation groups
    E. BOM version

Show Answer Hide Answer

Suggested Answer: D
 