Which two actions should you perform to meet the requirements?

1 Posts
1 Users
0 Likes
105 Views
(@sitesmario)
Posts: 734
Noble Member
Topic starter
 

A buying agent is evaluating vendors for sourcing an item. Prices and lead times vary by vendor.

The buyer requires that the planning engine be set up to provide the best price while considering the lead time.

Manual correction must not be required after planned purchase orders have been created.

Which two actions should you perform to meet the requirements? Each correct answer presents part of the solution.

  • A . Use Planning Optimization.
    B. Use built-in master planning.
    C. Set Purchase trade agreements.
    D. Set the default vendor on the item.
    E. Set the override lead times on the item to yes.

Show Answer Hide Answer

Suggested Answer: C,D
 