Which of the following relationship types would you consider using for a Main Contractor on a building construction project, who will be responsible for co-ordinating the activities of other suppliers?

1 Posts
1 Users
0 Likes
76 Views
(@rippebrain)
Posts: 721
Noble Member
Topic starter
 

Which of the following relationship types would you consider using for a Main Contractor on a building construction project, who will be responsible for co-ordinating the activities of other suppliers?

  • A . partnership
    B. transactional
    C. closer tactical
    D. co-destiny

Show Answer Hide Answer

Suggested Answer: C

Explanation:

in tiered supply chains, a closer-tactical relationship could be used between a buyer and a supplier who will be responsible for co-ordinating the activities of other suppliers (p.8 of the textbook).
 