Which of the following relationship types would you consider using for a Main Contractor on a building construction project, who will be responsible for co-ordinating the activities of other suppliers?
- A . partnership
B. transactional
C. closer tactical
D. co-destiny
Suggested Answer: C
Explanation:
in tiered supply chains, a closer-tactical relationship could be used between a buyer and a supplier who will be responsible for co-ordinating the activities of other suppliers (p.8 of the textbook).
Explanation:
in tiered supply chains, a closer-tactical relationship could be used between a buyer and a supplier who will be responsible for co-ordinating the activities of other suppliers (p.8 of the textbook).