Which of the following controls would an internal auditor consider the most relevant to reduce risks of project cost overruns?
- A . Scope change requests are reviewed and approved by a manager with a proper level of authority.
B. Cost overruns are reviewed and approved by a control committee led by the project manager.
C. There is a formal quality assurance process to review scope change requests before they are implemented
D. There is a formal process to monitor the status of the project and compare it to the cost baseline
Suggested Answer: D